Making space for the main refurbishment.
MPH’s involvement began with an initial package of mechanical pipework and drainage enabling works in the basement, at Level 4 and on the roof. In the basement car park, the required heating and chilled-water flow-and-return diversions were arranged away from new partition lines, allowing redundant sections to be removed after reconnection.
The upper-level works were more sensitive. The fourth-floor tenant was to remain operational while pipework in the main and secondary risers and roof areas was progressively isolated, drained down, adapted and stripped out. Sequencing was essential to protect retained heating and cooling supplies while creating space for the replacement systems.