← All projects
Commercial CAT B Fit-Out

The Sky Hub

The Sky Hub, London
Project overview / 01

Supporting a new workplace for Hartree Partners.

Located above the Victoria Station complex, the SkyHub development provides contemporary office accommodation at Buckingham Palace Road. Hartree Partners' Level 8 project involved adapting a shell-and-core space into a new Category B workplace.

Working under Mala Engineering Ltd, with Parkeray as Principal Contractor, MPH was responsible for the public health installation package: above-ground foul drainage, cold water distribution and hot water services integrated with the existing base-build infrastructure.

Location
SkyHub, Level 8 London Victoria
Sector
Commercial CAT B Fit-Out
Principal Contractor
Parkeray
MEP Contractor
Mala Engineering Ltd
Client
Hartree Partners
Installation summary

Project at a glance

L08
Tenant fit-out level
03
Public health workstreams
PUMPED
High-level foul drainage strategy
10 / 15 L
Specified local hot-water units
The engineering / 02

Complex routes. Practical public health solutions.

01 / Foul Drainage

A pumped drainage strategy for restricted floor voids.

The new workplace required above-ground foul drainage serving tea points, staff pantries, the prayer room, cleaners' facilities and associated equipment. The available floor void and the position of existing connections made conventional gravity drainage difficult to accommodate.

The Stage 3 engineering strategy therefore called for wastewater to be pumped to a high-level route, before falling by gravity to the existing stacks within the WC cores. MPH's drainage package required careful coordination of pump locations, routes and connections with the surrounding building services.

02 / Drainage Connections

Integrating new waste routes with existing stacks.

The proposed foul drainage arrangement included separate high-level ventilation pipework connected back to the relevant core stacks. Routes also needed to accommodate access fittings, changes of direction and future maintenance.

Because these connections interfaced with retained landlord infrastructure, pipework setting-out and coordination with the wider mechanical team were central to a practical installation.

03 / Cold Water

Extending boosted cold water services.

MPH's cold water package involved extending distribution from existing boosted cold water (BCWS) risers within the WC cores to new staff pantries, tea points, sinks and ancillary facilities.

The specified connection arrangements incorporated pressure-reducing valves, isolation and backflow protection, with solenoid isolation and pulse metering interfaces to the wider leak-detection and building controls strategy. These elements required coordinated setting-out and accessible valve positions.

04 / Hot Water

Local water heating for new workplace facilities.

The design adopted local electric point-of-use water heaters rather than a new central hot-water distribution network. The Stage 3 specification identified 10- and 15-litre units within low-level cupboards serving pantry, tea-point and other designated areas.

MPH's hot water package covered associated copper distribution and local equipment connections, with the engineering requirements addressing isolation, safety fittings and controlled outlet temperatures.

05 / Coordination

Public health services within a considered fit-out.

The architectural brief called for services to be discreetly integrated within partitions, furniture and constrained ceiling and floor voids, while maintaining practical access to valves, pumps and drainage components.

Across all three workstreams, MPH's involvement supported the integration of new public health infrastructure into the CAT B office layout and the existing building services.

MPH’s contribution / 03

Our scope of works.

  • Above-ground foul drainage for tea points, pantries and ancillary facilities
  • Pumped wastewater arrangements within restricted floor voids
  • High-level discharge distribution to existing WC core drainage stacks
  • Dedicated foul drainage ventilation pipework
  • Drainage connections, rodding and maintenance access provisions
  • Connections to existing boosted cold water (BCWS) risers
  • Domestic cold water distribution to new staff facilities
  • Isolation, pressure-control and backflow-protection provisions
  • Coordination of water metering and leak-detection interfaces
  • Local point-of-use electric hot-water heater connections
  • Hot-water copper distribution and sanitary outlet connections
  • Coordination with existing base-build services and CAT B fit-out